our business units + des + energy advisors + commissioning services + field engineering + day 2 services
 
   


Our Projects

   
   
Hunterdon County Retro-Commissioning
Field Engineering Services

Project Profile:
Project:   Hunterdon County Municipal Building
Owner:   Hunterdon County
Project Type:   Administration Building
Square Footage:   115,000 sf
Payback:   1.8 years

Project Details:
It was never a secret when county director of roads and bridges, John Glynn, had a tuna fish sandwich for lunch.  The aroma lingered in the air for days.  Some of his co-workers in the county administration building on Route 12 have complained that the building is sometimes too hot or too cold.  And county freeholder George Melick has been a vocal critic of what some people call Route 12 "chick coop," largely because of its high energy costs.

On Tuesday, the county freeholders learned that all the problems share the same root:  heating, ventilation and air conditioning systems that haven't been optimized.

The firm Dome-Tech of Edison is investigating and assessing the building's energy usage problems.  "We uncover comfort issues and high energy costs," said Bruce Curtis, an engineer with the firm.  When he's done with assessing a building, lower maintenance, lower energy costs and better air quality reward those who follow his recommendations, he said.

Dome-Tech's work isn't cheap.  A study of the 115,000 sf justice center cost the county $73,000 and the company's work at the 27,000 sf administration building cost $14,000.

But energy isn't cheap either.  The freeholders paid $279,000 last year in energy costs for the justice complex and $56,000 at the administration building.  The good news is that JCP&L will pay half of Dome-Tech's fee, and Mr. Curtis said that the county will recoup its expense in less than two years through energy savings.  He expects the county's energy savings will be about 10% at the administration building and 45% at the justice complex.

There is no one factor that's causing the excessive energy bills.  Instead, it's a combination of factors, some of which can be remedied as easily as re-programming an air-conditioning control unit or adjusting the speeds of fans.  Others, such as what Mr. Curtis called "design defects" at the justice center may cost more to correct.  Mr. Curtis said that in some cases, improper materials were used or the original engineering designs weren't followed.  But he said following his recommendations will result in more than $127,000 in annual energy savings.

The problems were not a complete surprise to county officials.  County counsel Guy DeSapio told the board that about $90,000 of payments to the contractor of the justice center have been withheld because of the concerns, but he admitted that it may cost more than that to correct.  Project administrator Frank Bell said payments to the electrical contractor at the administration building have also been withheld.

The freeholders plan to conduct similar studies other otehr county buildingsincluding includign the south and north branches of the county library, the jail and the historic courthouse, which is now undergoing renovations.

"They're finding the savings," said freeholder George Melick.  "This is the taxpayer's money we're saving."